The City of Tigard will design and construct a new water reservoir. This will ensure enough healthy, safe water to:
- Keep pace with the city’s growth
- Meet peak demand periods
- Navigate emergencies and natural disasters
This project includes three major pieces:
- A fully-buried 4.5-million gallon concrete drinking water reservoir at Sunrise Park – this is referred to as Reservoir 18
- A new pump station at Water Site 13 to deliver drinking water to the new reservoir – this is referred to as Pump Station 13, and
- Installation of distribution piping upgrades along two routes within the surrounding neighborhoods – these are referred to as the East and West Piping Upgrades
The main work areas are as follows:
- Reservoir 18 work will take place at Sunrise Park (15005 SW Sunrise Lane)
- Pump Station 13 work will take place at Water Site 13 at the southern end of SW 154th Ave.
- West Piping Upgrades will take place in SW Snapdragon Ln, SW Uplands Dr, SW Rockrose Ln, and SW Yarrow Way.
- East Piping Upgrades will take place in SW Wintergreen St, SW 153d Terr, SW Roundtree Dr, SW Menlor Ln, SW Fern St, and SW 135th Ave.
What’s Happening Now:
Project Update (September 11, 2024)
- Construction is underway and is estimated to be complete by June 2025.
- Reservoir 18: Tank construction is completed. The contractor is currently backfilling the reservoir. Starting in Late September, in order to ensure public safety, the park will be closed to the public as final grading and site restoration take place. This closure will last through approximately February 2025.
- Pump Station 13: Construction began in June 2023 and is expected to be complete by December 2024.
- Piping Upgrades: The contractor has completed installing new piping in the project area. Final surface restoration on Sunrise Lane and SW 154th Ave will be completed by December 2024.
- Expect increased traffic on SW 150th Ave, SW 154th Ave, and SW Sunrise Lane as equipment is delivered and construction activities begin. During Piping Upgrade construction, expect intermittent traffic interruptions and detour routes from the above mentioned streets.
Project Photos Update - December 12, 2023
Project Photos Update: October 30, 2023
Ask a question to the project team.
Page last updated: 12 Sep 2024, 04:17 PM